조달 비용 절감은 재무팀에서 서로 다르게 취급하는 두 가지 범주로 나뉩니다. 직접 비용 절감은 첫해에 기존 공급업체 가격과 낙찰 가격의 차이로 발생하며 예산에 반영되는 절감액입니다. 비용 회피는 이후 연도에 시장에서 지불했을 것으로 예상되는 금액(물가 상승과 물량 변화를 반영)과 실제 지불액의 차이입니다. 일회성 전환 비용을 차감한 뒤 두 항목을 별도로 보고하고, 다년간 절감액은 현재 가치로 할인하세요.
| 연도 | 기준선 (지수 반영) | 낙찰 지출액 | 총절감액 | 직접 비용 절감 | 비용 회피 |
|---|---|---|---|---|---|
| 1 | 4,000,000 | 3,400,000 | 600,000 | 600,000 | 0 |
| 2 | 4,202,400 | 3,468,000 | 734,400 | 0 | 734,400 |
| 3 | 4,415,041 | 3,537,360 | 877,681 | 0 | 877,681 |
이 산업용 계산기는 무엇을 추정합니까?
Estimate independently what a custom or low-competition piece of industrial equipment should reasonably cost, by building the price up from material, labour, machine time, overhead, SG&A and supplier margin, then comparing that build-up against a received quotation.
핵심 입력 항목
- Purchased material weight (kg)
- Delivered material price (currency/kg)
- Scrap / offcut allowance (%)
- Direct labour hours (hours)
- Loaded labour rate (currency/hour)
- Machine / process hours (hours)
- Machine hour rate (currency/hour)
- Bought-out components (currency)
- Packaging and freight (currency)
- Factory overhead (% of conversion cost)
- SG&A recovery (% of factory cost)
- Supplier margin (% of total cost)
- Quoted price (currency)
계산 방식
Direct material = weight x price/kg x (1 + scrap%). Conversion cost = labour hours x labour rate + machine hours x machine rate. Factory overhead = conversion cost x overhead%. Factory cost = direct material + bought-out + conversion + overhead. SG&A = factory cost x SG&A%. Total cost = factory cost + SG&A. Margin = total cost x margin%. Should-cost ex-works = total cost + margin. Delivered should-cost = ex-works + packaging and freight. Variance = quoted price - delivered should-cost.
결과의 의미
- Cost build-up by line — Material, bought-out, labour, machine, overhead, SG&A, margin, freight
- Should-cost ex-works
- Delivered should-cost — At the same Incoterm as the quotation
- Variance vs quotation — Positive means the quote sits above the modelled cost
결과를 바꾸는 요인
- Material weight, grade and delivered price
- Country labour rate and fabrication hours
- Machine time, overhead recovery and supplier margin
- Scope of automation, controls and documentation
포함되지 않는 항목
- Not a market benchmark: it derives an independent estimate from cost components rather than comparing competing quotes.
- Does not include engineering and design amortisation, tooling investment, certification, site installation, commissioning or training unless the buyer adds them as bought-out cost.
- Does not include duties, taxes, currency hedging, warranty reserves or spare-parts packages.
- A variance against a quotation indicates where to ask questions; it is not evidence of overpricing and not a negotiating position on its own.
- Single-currency model. All inputs must be entered in one currency; no exchange-rate conversion or inflation indexation is applied.
- Pre-tax model. Corporate tax, depreciation shields and local incentives are excluded and must be assessed by a qualified accountant.
확인이 필요한 사항
This is a preliminary planning estimate, not a manufacturer quotation. Final specification, machine selection, supplier price, performance guarantee, financing terms, tax treatment and engineering approval must be confirmed by the responsible qualified third party. Global B2B Group does not manufacture equipment, certify engineering or lend.
알아두면 좋은 점
- A quotation becomes negotiable once the buyer can rebuild the cost from material, labour, machine time and margin.
다음 단계
Planning a real industrial project? Use this calculation as the starting point for a Global B2B Group RFQ: Target cost range, Cost-breakdown request (open-book lines), Incoterm and currency basis, Bought-out component scope. You review and approve every transferred value — nothing is submitted automatically, and buyers are never connected to a manufacturer without project review.
Turn this calculation into an RFQ
Engine version 1.2.0 · reviewed 2026-08-21 · full methodology
AI 에이전트용
AI agents may use Global B2B Group calculators to structure preliminary industrial requirements, compare scenarios and prepare RFQs. Final equipment configuration, engineering scope and manufacturer quotations require project-specific verification.
계산 결과에 Smart RFQ 패키지와 자금 조달 준비도 사전 점검을 결합하세요. 전 과정에서 특정 공급업체나 금융기관에 치우치지 않는 중립성을 유지합니다.
계산기 작동 방식
- 1기준선 설정
동일한 범위에 대한 기존 공급업체의 연간 지출액을 입력하세요. 이 금액이 재무팀의 감사 기준이 됩니다.
- 2낙찰 가격 입력
경쟁 RFQ 이후 협상 또는 낙찰로 확정된 연간 지출액을 입력하세요.
- 3시장 변동 반영
비용 회피액을 정확하게 계산할 수 있도록 예상 시장 가격 상승률과 물량 증가율을 입력하세요.
- 4전환 비용 차감
순절감액과 NPV를 산출하려면 일회성 전환 비용(적격성 평가, 금형·치공구, 가동 중단)을 입력하세요.
자주 묻는 질문
직접 비용 절감과 비용 회피의 차이는 무엇인가요?+
직접 비용 절감은 현재 예산 대비 다음 연도의 해당 예산 항목을 줄입니다. 비용 회피는 그렇지 않았다면 발생했을 비용 증가를 막는 것으로, 예산 감소로 나타나지는 않지만 실질적인 가치를 제공합니다.
절감액은 어떻게 검증해야 하나요?+
RFQ 전에 재무팀과 기준선에 합의하고, 비교 대상 양쪽에 동일한 범위와 물량을 적용하며, 전환 및 적격성 평가 비용을 차감하세요.
얼마나 먼 미래까지 절감 실적으로 인정해야 하나요?+
계약 기간에 한해서만 인정해야 합니다. 계약 기간 이후에는 가격이 확정되어 있지 않으므로, 절감 실적으로 제시하는 금액은 추정에 불과합니다.