FAT vs SAT: acceptance testing for machinery

Agree how equipment will be proven before you sign the contract.

Published 2026-09-28·Updated 2026-10-13·Global B2B Group Editorial Standards Board·~5 min read
The same machine tested at the factory and then checked by engineers after installation on site

What is the difference between FAT and SAT?

The difference is where, when and against what conditions the equipment is proven. FAT happens at the supplier's works before shipment, usually with simulated or limited product. SAT happens after installation in the buyer's plant, with real utilities, upstream and downstream equipment, product and operators.

Use FAT to catch build, control and safety problems while they are cheap to fix. Use SAT to prove the installed performance the contract promises. Passing FAT does not prove site performance, and SAT cannot recover the time lost when a defect that FAT should have caught is found on site.

  • Location — FAT: supplier's factory; SAT: buyer's site
  • Timing — FAT: before shipment; SAT: after installation and commissioning
  • Conditions — FAT: simulated or sample product; SAT: real product, utilities and line integration
  • Typical sign-off — FAT: release for shipment; SAT: handover and final payment milestone

What does a factory acceptance test check?

FAT is the last chance to find problems cheaply, before crating and shipping.

  • Mechanical build and documentation against the specification
  • Control logic, safety functions and alarms
  • Dry runs or test runs with representative material where possible
  • Agreed punch list before release for shipment

What does a site acceptance test check?

SAT confirms installed performance: output rate, quality, utility consumption and integration with upstream and downstream equipment, measured under conditions agreed in advance.

What should the RFQ say about acceptance?

  • Test location, duration and who attends
  • Measurable criteria: output, reject rate, uptime, consumption
  • Materials the buyer must supply for testing
  • Link between acceptance milestones and payment
  • Remedies if criteria are not met

Packaging lines, production lines and calculators

Global B2B Group's main line is packaging and production lines — for fish, shrimp, greenhouse produce and other agri-food products — plus custom machinery, for projects from USD 250,000 with human review before any supplier outreach.

Packaging and production-line guides

Estimate before you send an RFQ

Sector projects go to our specialist platforms

Sector projects such as cold rooms, hatcheries, fish farms, greenhouses or feed mills go to the matching specialist platform. Packaging lines, custom machinery, multi-sector projects, CAPEX planning and financing preparation stay with Global B2B Group, so each buyer has one route and the platforms never compete.

Quick questions

Can SAT replace FAT?+

Not safely for custom or high-value equipment. SAT runs after shipping and installation, so any defect found then costs more time and money to correct. Skipping FAT is a risk decision the buyer should take explicitly.

Is there a standard for FAT and SAT?+

For automation systems in the process industry, IEC 62381 describes FAT, site acceptance and integration testing. Many machinery contracts use it as a reference, but the project's own written acceptance criteria still govern.

Is FAT always required?+

It is strongly recommended for custom or high-value equipment. For standard catalogue items, a documented test report may be sufficient.

Who pays for FAT travel?+

It is negotiable. State it in the RFQ so all suppliers quote on the same basis.

Can payments be tied to FAT and SAT?+

Yes. Many contracts link a payment milestone to successful FAT and the final milestone to SAT sign-off.

Why does a packaging line need both FAT and SAT?+

FAT proves the machine works at the builder's site; SAT proves it works on your floor with your product flow, utilities and operators. Speed and accuracy can change once the line is integrated, so both should have measurable criteria.

Summary

  • FAT proves the machine at the factory; SAT proves it in your plant
  • Define measurable acceptance criteria in the RFQ
  • Link milestones and remedies to test results

Global B2B Group is an independent, human-reviewed procurement channel — not a manufacturer, contractor or lender. Figures and methods here are general guidance; confirm project-specific details with qualified advisers.

Continue with our commercial resources

Hand-picked next steps for this topic — special purpose machinery and industrial project financing.

Email updates

Sourcing intelligence and buyer guides, by email

Choose the topics, language and frequency you want. We send a confirmation link first and nothing else until you confirm. Each digest links to the full articles on the site.

Signing up is not a sourcing request.

Sector updates from our specialist platforms

Topics
How often

We use your email only for these updates and never share it with suppliers. Every email has an unsubscribe and preferences link. Privacy policy

Share this article