FAT for custom machinery: what to test and when to pay
A custom machine has no track record. The factory acceptance test is where you prove it works before it ships.

Why is FAT more important for custom machines?
Standard machines have references running the same model. A custom machine is often the first of its kind, so the FAT is the first real evidence that the design meets your process.
Which criteria should the FAT measure?
Every criterion should be measurable and linked to the requirement in your RFQ.
- Output per hour at the stated product format
- Continuous run time without stoppages
- Reject or defect rate
- Format changeover time
- Safety functions, guarding and emergency stops
- Documentation and software backups delivered
What product should be used for testing?
Send enough of your real product or packaging to run a meaningful test. Tests on substitute material often hide problems that appear on site.
What happens if the machine fails FAT?
The builder corrects the issue and the test is repeated at its cost, within an agreed period. Repeated failure should trigger remedies defined in the contract.
Packaging lines, production lines and calculators
Global B2B Group's main line is packaging and production lines — for fish, shrimp, greenhouse produce and other agri-food products — plus custom machinery, for projects from USD 250,000 with human review before any supplier outreach.
Packaging and production-line guides
- How to compare food packaging line proposals
- Food processing line planning: hygiene, capacity, packaging
- Packaging automation ROI
- Fish & shrimp packaging line profile
- Special-purpose and custom machinery
- Industrial machinery and production lines
Estimate before you send an RFQ
- Line throughput calculator
- Project delay cost calculator
- CAPEX calculator
- Start a project or build a structured RFQ
Sector projects go to our specialist platforms
Sector projects such as cold rooms, hatcheries, fish farms, greenhouses or feed mills go to the matching specialist platform. Packaging lines, custom machinery, multi-sector projects, CAPEX planning and financing preparation stay with Global B2B Group, so each buyer has one route and the platforms never compete.
- ColdMatch Group — Cold storage, refrigeration and cold-chain infrastructure
- HatchMatch Group — Poultry farms, hatcheries and poultry infrastructure
- FishMatch Group — Fish farming, shrimp farming and aquaculture systems
- SeedMatch Group — Greenhouses, irrigation, protected agriculture and seed
- FeedMatch Group — Animal feed, ingredients and feed mills
Quick questions
Does passing FAT mean the machine is accepted?+
No. Final acceptance normally follows the site acceptance test (SAT) after installation.
Can FAT be witnessed remotely?+
Remote witnessing is possible for simple checks, but in-person attendance is safer for first-of-a-kind machines.
Who pays for a repeated FAT?+
Normally the builder, if the first test failed against agreed criteria.
What should a FAT for a food packaging line test?+
Run the line with your real product and packaging film or trays: output per minute, weight or fill accuracy, seal integrity, reject rate, changeover time between formats and a sustained run. Agree pass/fail values in the RFQ.
Summary
- Agree measurable FAT criteria in the contract
- Test with your real product
- Link the pre-shipment payment to a signed, passed FAT
Global B2B Group is an independent, human-reviewed procurement channel — not a manufacturer, contractor or lender. Figures and methods here are general guidance; confirm project-specific details with qualified advisers.
Continue with our commercial resources
Hand-picked next steps for this topic — special purpose machinery and industrial project financing.