Structure your CAPEX project into modules, sourcing options and milestones
Set your sector, capacity and readiness. The planner returns an equipment module breakdown with indicative CAPEX shares and lead times, a sourcing comparison, and the milestone plan you need to clear before issuing RFQs.
Equipment modules
Cold storage & industrial refrigeration projects split into 6 work packages. Shares are indicative percentages of installed CAPEX under the multi-supplier packages model.
| Module | Share | Indicative CAPEX | Lead time | Supply route |
|---|---|---|---|---|
Civil works & foundationsCritical path Site preparation, slab, drainage, docks and yard. | 20% | $380K – $900K | 12–24 wks | Local contractor |
Insulated envelope & doors Panels, vapour barrier, cold doors, dock levellers and seals. | 16% | $304K – $720K | 10–18 wks | Specialist OEM |
Refrigeration plantCritical path Compressor pack, condensers, evaporators, refrigerant system and controls. | 30% | $570K – $1.4M | 16–30 wks | Specialist OEM |
Racking & material handling Racking, forklifts or shuttle systems, and pallet flow layout. | 13% | $247K – $585K | 8–16 wks | Specialist OEM |
Electrical, power & backupCritical path Transformer, switchgear, distribution, generator and metering. | 12% | $228K – $540K | 12–26 wks | System integrator |
Monitoring, WMS & compliance Temperature monitoring, alarms, WMS interface, HACCP documentation. | 9% | $171K – $405K | 6–12 wks | System integrator |
Longest single lead time in this scope is 30 weeks — order that package first.
Sourcing options
- Indicative CAPEX
- $3.6M
- RFQ packages
- 1
- Schedule
- ~47 wks
- + Single point of responsibility
- + Bankable performance guarantee
- + Lowest internal workload
- − 8–15% wrap premium
- − Less price transparency per package
- − Harder to swap sub-suppliers
- Indicative CAPEX
- $3.2M
- RFQ packages
- 6
- Schedule
- ~51 wks
- + Best unit pricing per package
- + Full technical transparency
- + Direct OEM relationships
- − Interface risk sits with the buyer
- − Needs an owner's engineer
- − More procurement effort
- Indicative CAPEX
- $3.4M
- RFQ packages
- 3
- Schedule
- ~37 wks
- + Lower day-one capital
- + Revenue starts earlier
- + De-risks demand assumptions
- − Higher lifetime cost per unit
- − Second-phase price risk
- − Requires oversized utilities upfront
Readiness milestones
1 of 8 gates cleared. Next: Site secured & surveyed — Land control, soil, access, and utility availability confirmed in writing.
- DefineWeek 0Project brief & capacity targetAgree output, product mix and service levels the facility must deliver.
- DefineWeek 3Site secured & surveyedLand control, soil, access, and utility availability confirmed in writing.
- DefineWeek 4Owner's team appointedProject manager plus owner's engineer or technical advisor mandated.
- ValidateWeek 8Concept layout & mass balanceBlock layout, process flow and utility loads sized per module.
- ValidateWeek 10CAPEX/OPEX model & paybackInstalled CAPEX by module, operating model, payback and sensitivity.
- SourceWeek 13Technical specification packPer-module specs, standards, guarantees and evaluation criteria.
- SourceWeek 15RFQ issued to qualified suppliersPackages released with a common bid format and comparison sheet.
- FinanceWeek 18Financing structure mandatedDebt/equity split, ECA or development finance route and term sheet.
- FinanceWeek 20Permits & regulatory approvalsBuilding, environmental, food-safety or veterinary approvals filed.
- ExecuteWeek 24Contract award & down paymentTechnical alignment closed, contracts signed, advance payments released.
- ExecuteWeek 40FAT, installation & SATFactory acceptance, shipping, installation, commissioning and training.
Global B2B Group does not sell equipment and does not rank suppliers. Module shares, lead times and programme durations are screening benchmarks — confirm every figure with quotations and project-specific engineering.