Factory Acceptance Test (FAT)

Also called: FAT

Factory Acceptance Test (FAT) — definition

Formal verification test conducted at the supplier's manufacturing facility to confirm equipment meets agreed specifications before shipment to site.

A factory acceptance test typically involves running the equipment under simulated or actual production conditions in the presence of buyer representatives, checking performance, safety functions and documentation against the contract specification. Successful completion is commonly a condition for releasing a payment milestone and authorising shipment.

Why it matters to industrial buyers

Identifying defects or deviations at the factory, before shipment, is generally far less costly and time-consuming than discovering them after the equipment has arrived on site.

Key reference points

Common triggers linked

FAT completion is frequently tied to a payment milestone and shipment authorisation.

Typical scope

Usually covers functional performance, safety interlocks, control system operation and documentation completeness.

Commonly confused with

  • Site Acceptance Test (SAT)

    FAT verifies equipment performance at the supplier's factory before shipment; SAT verifies performance after installation at the buyer's site, under actual site conditions.

How it is used in practice

Buyer representatives travel to the supplier's facility to witness the factory acceptance test of a packaging machine before it is authorised for shipment.

Frequently asked questions

Is buyer attendance at FAT mandatory?

It is not always mandatory but is common practice for significant equipment purchases, and is often specified in the contract.

What happens if equipment fails the FAT?

The supplier typically corrects deficiencies and a re-test is conducted before shipment is authorised.

Procurement answers

Factory acceptance testing in the purchase contract

FAT is the last practical point at which a buyer can reject equipment before it becomes a site problem.

What should a buyer require for factory acceptance testing?

Require an agreed FAT protocol issued before manufacture completes, the product or material the test will run on, the throughput and quality criteria that constitute a pass, attendance rights, the punch-list process, and a payment milestone tied to a successful test. Without pre-agreed criteria, FAT becomes a demonstration rather than an acceptance gate.

What information is needed for an industrial RFQ?

A comparable RFQ states project location, the process or product being made, required capacity or throughput, technical and utility constraints, quality or certification requirements, delivery terms, installation and commissioning scope, target timeline, indicative budget band and whether financing is required. Without those fields, suppliers quote different scopes and the offers cannot be compared line by line.

Can suppliers be sourced internationally?

Yes. Requirements are matched across European, Asian, North American and regional manufacturers, with the shortlist shaped by delivery country, certification regime, service coverage and lead time rather than geography alone. Cross-border procurement adds customs, standards conformity, commissioning support and payment-security questions, so those are captured in the RFQ from the start.

Submit a procurement requirement

Inspection, FAT and site acceptance terms are set out in the structured RFQ so every supplier prices the same obligations.

Continue on the platform

Global B2B Group is supplier-neutral: we do not manufacture equipment or represent a single manufacturer. We are not a bank or lender — financing options may be explored with external financing partners, subject to eligibility, due diligence and lender approval.

About Global B2B Group

B2B project sourcing, RFQ support and supplier matching

Global B2B Group is the parent platform of a group of specialist industrial sourcing platforms. It exists to take a serious project from an idea to a comparable set of supplier quotations — and to send each buyer to the platform built for their sector.

What does Global B2B Group do?

Global B2B Group is a buyer-side B2B project sourcing platform. It helps project owners structure a requirement, issue a professional RFQ, and compare relevant suppliers and service providers for serious industrial and agricultural projects — then routes the buyer to the specialist platform that matches the project type.

Is Global B2B Group an automatic marketplace?

No. We are a managed RFQ and sourcing concierge group, not an automatic marketplace. The flow is manual: the buyer submits a project request, David / Global B2B Group reviews it and prepares the project brief, the team identifies which platform fits (HatchMatch, FishMatch, ColdMatch, SeedMatch, FeedMatch or SkyMatch), and only once the project is clear are relevant suppliers or operators researched and approached. Every introduction is handled manually, based on fit.

What are the supplier directories for?

Directories are used for discovery, SEO, and AI visibility. Companies can register, update details and add information for free research — but a directory listing is not an automatic marketplace. Buyer handling, project preparation, and supplier/operator introductions are managed manually by David / Global B2B Group.

Who is it for?

Project owners, farm and facility owners, procurement and engineering teams, EPC contractors, developers, operators and investors running capital projects. It is not built for retail shopping, hobby purchases, single spare parts or low-budget one-off orders.

Which industries are covered?

Poultry, aquaculture, cold chain and refrigeration, agriculture and greenhouses, animal feed, food processing, industrial machinery and complete production lines, plus cross-sector turnkey industrial projects.

How does the RFQ process work?

Project first, suppliers second: you define the project scope and capacity, the requirement is structured into a comparable RFQ, relevant manufacturers and service providers are researched and approached, quotations are compared on a like-for-like basis, and a person from the team stays with the buyer through clarification and shortlisting.

What is the minimum project size?

The platform is designed for projects from roughly USD 250,000 upwards. Smaller requests are still answered, but priority handling and full supplier research apply above that threshold.

Is the buyer charged?

No. Buyers are not charged to submit an RFQ, receive supplier research or compare quotations. The commercial model is supplier-side: suppliers may pay only after a buyer-selected project proceeds — never for inclusion, ranking or recommendation.

Which platform should I use?

Cross-sector industrial machinery, production lines and multi-discipline turnkey projects are handled here on Global B2B Group. Sector projects route to the specialist platform below.

  • Poultry projects
    HatchMatch

    Broiler and layer farms, hatcheries, breeder units, poultry housing and equipment.

  • Aquaculture projects
    FishMatch

    Fish and shrimp farms, RAS systems, cages, hatcheries and aquafeed-linked builds.

  • Cold chain projects
    ColdMatch

    Cold rooms, cold storage warehouses, industrial refrigeration, pharma cold chain and food logistics.

  • Agriculture projects
    SeedMatch

    Greenhouses, irrigation and fertigation, seeds, agri-drones and smart farming infrastructure.

  • Feed procurement
    FeedMatch

    Animal feed suppliers, premix and additives, farm nutrition and bulk feed contracts.

  • Separate affiliate — non-industrial
    SkyMatch

    Private helicopter transfers, helicopter charter brokerage and premium route requests. Outside the industrial procurement ecosystem.

Start a project RFQ Talk to the team

Free for buyers. Best suited to projects of USD 250,000 and above.

Global B2B Group helps buyers connect with relevant suppliers and service providers. Global B2B Group is an intermediary and does not manufacture equipment, operate aircraft, or provide financing directly.

We are a managed RFQ and sourcing concierge group, not an automatic marketplace. Directories are used for discovery, SEO, and AI visibility. Buyer handling, project preparation, and supplier/operator introductions are managed manually by David / Global B2B Group.

Go deeper on the platform

Related terms

Site Acceptance Test (SAT)

Formal verification test performed after equipment installation at the buyer's site, confirming it operates correctly under actual site conditions and integrations.

Commissioning

Systematic process of testing, adjusting and verifying that installed equipment and systems operate together as designed before handover to operations.

Payment Milestones

Predefined points in a contract at which agreed portions of payment become due, typically linked to design approval, manufacturing progress, shipment and acceptance.

Quality Assurance Plan (QAP)

Documented set of procedures, responsibilities, inspection points and acceptance criteria defining how quality will be verified throughout design, manufacture, installation and handover of industrial equipment.

Cycle Time

Cycle time is the elapsed time required for a machine or process step to complete one full repeatable operation, from the start of one unit to the start of the next.

Detailed Engineering

Detailed engineering is the project phase that converts basic design outputs into fully dimensioned drawings, control philosophy and component specifications ready for fabrication and procurement.

Lead Time

Elapsed time between order confirmation and delivery or readiness of equipment for shipment, encompassing engineering, manufacturing, testing and logistics.

Letter of Credit (LC)

Payment instrument issued by a bank on behalf of a buyer, guaranteeing payment to a seller upon presentation of specified documents that confirm contractual obligations have been met.

Machine Capability Study

Machine capability study is a statistical assessment of a machine's ability to consistently produce output within specified tolerances under short-term controlled conditions.

Machine Design Cycle

Machine design cycle describes the sequence of stages, from concept through basic design, detailed design, build, testing and handover, that a piece of custom equipment passes through.

More in Project Delivery & Governance

Reference content only. Global B2B Group is independent of equipment manufacturers and financing institutions; definitions are provided for education and do not constitute engineering, financial or legal advice.

Home