Custom Machine Development

Custom machine development converts a production requirement into a validated machine. Its phases are sequential for a reason: each one closes uncertainty that the next assumes as settled.

Direct answer

Requirements, concept, detailed design, build, FAT, installation, SAT and validation. Buyers control cost and schedule mainly in the first two phases.

What this discipline delivers

  • A user requirement specification (URS) defining what must be achieved, not how
  • A concept with cycle-time budget and risk assessment
  • Detailed mechanical, electrical and control design
  • A build with documented factory testing
  • Site installation, commissioning and validated handover

Method and stages

Phase 1 — Requirements

URS, product data, throughput, interfaces, acceptance criteria and constraints.

Phase 2 — Concept

Options, cycle-time budget, layout, preliminary risk assessment, budget estimate.

Phase 3 — Detailed design

Design freeze, drawings, schematics, software architecture, procurement of long-lead items.

Phase 4 — Build and FAT

Manufacture, assembly, software, factory acceptance test with real product.

Phase 5 — Install, SAT, validate

Site installation, commissioning, site acceptance and performance qualification.

Engineering and project considerations

  • Changes after design freeze cost multiples of changes before it
  • Real product samples must be available for concept and FAT
  • Long-lead components should be ordered against the schedule, not the budget cycle
  • Documentation and code ownership must be contractual
  • Design reviews with buyer participation at each phase gate

What to prepare before engaging engineering companies

  • URS in performance terms with measurable acceptance criteria
  • Product samples spanning the full variability range
  • Site constraints and interface data
  • Phase-gate schedule with buyer decision dates

What to measure

Adherence to phase gatesChange orders after design freezePerformance achieved at SAT

Frequently asked questions

What is a URS?

A user requirement specification states what the machine must achieve — throughput, quality, interfaces, compliance — without prescribing the design. It is the buyer's most powerful document.

Who writes the specification?

The buyer, ideally with independent engineering support. Specifications written by the supplier tend to describe what that supplier already builds.

Related engineering knowledge

Independent, buyer-side and supplier-neutral

Global B2B Group does not sell machines and does not represent equipment manufacturers. This material is published to help industrial organisations define the problem, prepare the specification and structure the investment before engineering partners are selected.