Project Delivery Intelligence · ~10 min read

Commissioning Strategy

Commissioning is frequently compressed into the schedule gap left over after construction runs long, which is the leading cause of rushed start-ups and early operating failures. A commissioning strategy defines sequencing, test protocols and acceptance criteria well before mechanical completion.

Executive summary

Sequence commissioning system by system — utilities before process, individual equipment before integrated lines — and define Factory Acceptance Test and Site Acceptance Test protocols with quantified acceptance criteria at the time equipment is ordered, not once it arrives. Protect the commissioning window as a fixed schedule element rather than a buffer absorbed by construction delay.

Factory Acceptance Testing at the vendor's facility catches defects before shipment, when correction is materially cheaper than after installation; skipping FAT to save schedule time typically shifts cost, not removes it.

Why projects fail without this

  • Commissioning window treated as flexible buffer absorbing construction delay
  • FAT protocols not defined until equipment is ready to ship
  • No system-by-system commissioning sequence, only a single 'commissioning phase' on the schedule
  • Utilities commissioning not completed before process equipment commissioning begins
  • Vendor commissioning support contracted late, creating availability risk
  • Acceptance criteria not quantified before testing begins

How disciplined teams run it

Factory Acceptance Testing

Tested at the vendor's facility before shipment, against acceptance criteria agreed at order placement.

Site Acceptance Testing

Re-verification after installation, confirming the equipment performs as tested at FAT under site conditions.

System-by-system sequencing

Utilities, then individual equipment, then integrated lines — not a single undifferentiated commissioning phase.

Vendor commissioning support

Contracted and scheduled well in advance to avoid availability conflicts across multiple concurrent projects.

Punch-list management

Formal categorisation of outstanding items by whether they block start-up, distinguishing critical from cosmetic.

Comparison table

Commissioning sequence and gating
StageScopeGate before proceeding
FATEquipment tested at vendor siteAcceptance criteria met and signed
Installation and pre-commissioningStatic checks, loop checksPunch-list critical items closed
SAT / utilities commissioningUtilities live, individual equipment energisedUtility capacity confirmed
Integrated / process commissioningFull line running under loadPerformance validation criteria met

Commissioning sequence and gating

Risks and governance considerations

  • Acceptance criteria agreed only at the point of testing, rather than at order placement, invite dispute when equipment underperforms
  • Commissioning compressed by upstream construction delay tends to produce rushed start-ups with unresolved punch-list items carried into operation
  • Utilities commissioned after process equipment risk masking process performance issues caused by inadequate utility supply
  • Vendor commissioning engineers are often shared across multiple client projects; scheduling conflicts should be identified and contracted against early

What to prepare

  • FAT and SAT protocols with quantified acceptance criteria, agreed at order placement
  • System-by-system commissioning sequence integrated into the master schedule
  • Vendor commissioning support contracted and scheduled in advance
  • Punch-list categorisation protocol distinguishing critical from non-critical items
  • Utilities commissioning plan completed before process equipment commissioning starts

What to measure

FAT pass rate on first attemptPunch-list items open at start-upCommissioning schedule adherenceTime from mechanical completion to first production

Frequently asked questions

Is FAT necessary if the vendor has a strong track record?

Track record reduces risk but does not eliminate the value of verifying the specific unit ordered performs to the agreed criteria before it is shipped and installed.

What should happen to open punch-list items at start-up?

Only non-critical items should remain open; critical items — anything affecting safety, product quality or equipment protection — should be closed before start-up proceeds.

How far in advance should vendor commissioning support be contracted?

Typically several months, particularly for specialised equipment where the vendor's commissioning engineers are shared across concurrent projects globally.

Related investment and financing knowledge

Continue on the platform

Educational, supplier-neutral and financing-neutral

Global B2B Group does not sell equipment and does not represent lenders, export credit agencies or development banks. This material is published to help industrial organisations plan, structure and prepare capital projects. It is general information for decision-making, not financial, legal or tax advice.

Explore the Industrial Investment Center

Home