Turnkey Poultry Processing Plant in the Middle East.
A greenfield 12,000-birds/hour poultry processing facility procured under turnkey EPC and financed by an OECD ECA — with FAT-first quality discipline.
Client profile & engagement record
- Client
- Vertically integrated poultry group (part family-owned, part regional investment fund), Middle East
- Scale at engagement
- ~2,100 employees, own breeder farms and feed mill, two national retail accounts
- Existing assets
- One 4,500 birds/hour line running three shifts at 105% of design capacity
- Client objective
- Greenfield 12,000 birds/hour processing line with Halal, HACCP and retailer-audit compliance
- Consultant role
- External food-engineering adviser led the FAT protocol and witnessed factory testing on the sponsor's behalf
- Global B2B Group role
- Structured the RFQ, ran manufacturer research and proposal normalisation, and supported financing-readiness documentation. Financing decisions were made solely by the institution.
Decision makers involved
- Board investment committee — CAPEX approval and delivery-model decision
- CFO — ECA-guaranteed loan, advance-payment guarantees and covenant testing
- Plant Director — throughput, yield and shift planning
- Head of Food Safety — Halal certification and cold-chain traceability
- External food-engineering adviser — FAT protocol owner
Engagement timeline
- Requirement
- Months 1–4 — FEED, throughput and product-mix specification
- RFQ issued
- Month 5 — turnkey LSTK brief to shortlisted European suppliers
- Proposals
- Months 6–8 — normalised comparison, financing readiness screened in parallel
- Award
- Month 9 — EPC award with 24-month warranty
- Completion
- Month 24 — first commercial slaughter
Engagement record reconciled with the project's FAT and acceptance documentation and approved by the sponsor before publication. Company name, site location and individual names are withheld under a confidentiality agreement; figures are rounded and published with the project owner's approval. Global B2B Group is supplier-neutral and does not manufacture, install, certify or lend.
Challenge
The sponsor's existing 4,500 birds/hour line ran three shifts at 105% design capacity and could not absorb forecast domestic demand growth. Halal certification and cold-chain traceability requirements from two key retail accounts made a piecemeal expansion uneconomic. The board approved a greenfield 12,000 birds/hour line on an adjacent parcel of land the sponsor already owned.
Strategy
Turnkey EPC was chosen deliberately. The sponsor had no in-house poultry-line engineering, the plant needed to be single-point-warranty for retailer audits, and lender preference (an OECD ECA) favoured a wrapped scope for limited-recourse structuring. The premium versus multi-contract was estimated at 9% — accepted by the executive committee against the risk profile.
- EPC wrap for single warranty and financeability
- Two-country corridor for evisceration and cut-up equipment
- Halal and retailer audit requirements embedded in specification
- Board-endorsed CAPEX ceiling and 8% contingency held outside contract
The delivery-model rationale followed the Turnkey vs Multi-Contract guide.
Supplier selection
Four full-line integrators were invited to a two-round RFQ. All four met technical minimums; two were dropped after reference-site visits (one for warranty-response evidence, one for supply-chain concentration on a sanctioned tier-2). The final award went to the supplier with the strongest post-award support model, not the lowest headline price.
- Two-round RFQ with technical + commercial evaluation
- Warranty response times verified with three independent reference sites
- Tier-2 supply chain screened for sanctions and concentration
- Final scoring: technical 40%, price 30%, warranty & service 20%, ESG 10%
Financing
The OECD ECA guaranteed 85% of the eligible equipment and services value. The commercial bank arranging the loan required an independent lender's engineer, an ESIA covering effluent and animal welfare, and a signed offtake structure with the sponsor's two retailer accounts. Financing was documented in parallel with the last two months of technical RFQ evaluation — the ECA structuring never became the critical path.
The offtake and lender-engineer requirements mirror the Project Financing Readiness checklist. Structural background is on the Export Credit Agencies pillar.
Execution
The contract included a formal Factory Acceptance Test at the supplier's works: three consecutive test days at contract throughput on live-carcass simulations, with the sponsor's veterinary lead present. FAT identified 11 non-conformances; 9 were closed at the supplier's cost before shipment, 2 were deferred to SAT with a signed deviation waiver. Site erection ran 3 weeks behind schedule due to imported-cladding customs delays; commissioning recovered 2 weeks through parallel utility handover. First commercial slaughter began 7 days after contractual date.
- FAT: 11 NCRs, 9 closed pre-shipment at supplier cost
- Imported cladding customs delay flagged early via risk register
- Retention of 10% held to end of 24-month warranty
- First commercial slaughter 7 days late vs 24-month plan
Lessons learned
- FAT at the supplier's works paid for itself several times over — the two deferred items would have blocked SAT.
- The wrap premium (9%) was cheaper than the estimated cost of managing 6+ package interfaces without in-house engineering.
- Running financing structuring in parallel with technical RFQ shaved an estimated 10 weeks off the critical path.
- The customs cladding issue is now a standing item on the sponsor's project risk register for every subsequent build.
- Retention held to warranty triggered one call on a controls issue — the mechanism justified the negotiation effort.
Executive takeaways
- Match delivery model to owner engineering depth and lender preference — turnkey EPC is often the right premium.
- FAT is the highest-leverage moment in the whole procurement — treat it as owner-controlled, not a supplier ceremony.
- Structure ECA finance in parallel with technical evaluation, not sequentially.
- Retention held to warranty is not a formality — it is the enforcement mechanism.
Related executive resources
Planning a similar project?
Global B2B Group can help you prepare a professional procurement strategy, identify qualified international suppliers, compare solutions objectively and explore suitable financing opportunities.
